Works estimation · Tendering · Agreements · Billing — one platform contact@estimotor.online
Home › Calculators › Earthwork

Earthwork Calculators — Excavation & Filling

Work out trench or pit excavation quantity by the mean-area method with the side slope of your choice, convert compacted fill into the loose quantity you must actually arrange, and understand how the schedule pays for extra lead and lift.

Two quick earthwork checks

Both calculators run entirely in your browser — nothing is sent anywhere. Enter dimensions in metres; results come out in cubic metres (and cft alongside).

🚜 A. Trench / pit excavation (with side slopes)

Enter the bottom dimensions of the cut and the depth. If the sides are battered, pick the slope and the calculator widens the top faces by 2 × slope × depth, then averages the two areas — the way most works offices record it in the details of measurement.

How this is worked out

ground level B (bottom) B + 2 × s × D (top) D slope s : 1

With a side slope of s : 1 (horizontal : vertical), each face of the cut steps out by s × D at ground level, on both sides. The plan area therefore grows from the bottom to the top, and the volume is taken as the depth times the average of the two areas:

Top length Lt = L + 2·s·D Top width Bt = B + 2·s·D Volume V = D × ( L·B + Lt·Bt ) / 2 … mean-area method

The mean-area figure reads marginally on the higher side compared with the exact prismoidal formula; for ordinary trenches and pits the difference is a fraction of a percent, which is why the simpler average is the customary record entry. For very deep or very large pits some departments insist on the prismoidal formula — check your manual.

Excavation is measured to the neat lines shown on the drawings. Working space, shoring allowance and over-break are paid only where the schedule item or the agreement specifically provides for them — do not add them here on your own.

🏗️ B. Filling — loose quantity to arrange

Fill is measured and paid compacted in place, but soil is carted and stacked loose. Enter the compacted fill volume from your details of measurement and the loose-to-compacted factor for the borrow material to see how much loose earth to arrange.

How this is worked out

When soil is dug out it bulks; when it is placed back in layers, watered and rammed or rolled, it compacts to less than its loose volume. The factor you enter is simply the ratio of the two states:

Loose quantity = Compacted volume × factor Typical factors: ordinary soil 1.20 – 1.30 (1.25 is a fair default) sand 1.10 – 1.15 moorum / gravelly soil ≈ 1.15 – 1.25

Use the factor established by field trials or your department's practice for the actual borrow material — clayey soils bulk more, clean sands hardly at all. Remember the payment item remains the compacted quantity; the loose figure is only your arrangement (carriage and stacking) planning number.

If the same excavated soil is being reused as fill, the excavation item and the filling item are measured independently — one from the cut, one compacted in the fill — and the balance goes to disposal. Never derive one from the other in the MB.

Lead & lift — how the schedule pays for carrying and raising earth

Every earthwork rate in a schedule of rates is built for a stated initial lead (the horizontal distance the spoil is carried) and a stated initial lift (the height through which it is raised). Move the earth farther, or raise it higher, and the labour involved goes up — so the schedule provides separate extra items that are added on top of the basic excavation or filling rate. Getting these extras right is a routine part of preparing the abstract of cost and, later, of checking an RA bill.

The usual conventions

  • Initial lead — commonly 50 m is deemed included in the basic rate. Beyond that, an extra is payable for each further slab of lead (often 50 m slabs up to a few hundred metres). Once the distance justifies a tipper or tractor-trolley, the manual lead extras stop and separate carriage items take over, paid in kilometre slabs for mechanical transport.
  • Initial lift — commonly 1.5 m is included. Every additional 1.5 m (or part thereof, where the schedule says so) attracts an extra-lift payment, because the earth must be re-handled or thrown in stages.
  • Measurement of lead — taken along the shortest practicable route from the centre of the excavation to the centre of the spoil heap or placement area, not along the route the labour actually walked. Record the route in the details of measurement so the bill checker can verify it.
  • Measurement of lift — the vertical difference between the level at which the earth is excavated and the level at which it is deposited, counted in slabs.

How the extra is computed

Extra-lead slabs = ceil( (actual lead − initial lead) / slab length ) Extra-lift slabs = ceil( (actual lift − initial lift) / slab height ) Payment for extras = affected quantity (m³) × scheduled extra rate per slab × number of slabs … then the agreement premium / rebate is applied, exactly as on the parent item.

Only the quantity that actually travelled the longer lead or climbed the higher lift is billed under the extra item — not the whole excavated quantity. On a large site with several spoil heaps the earthwork is therefore split lead-wise in the measurement record, and each portion carries its own extras. In an RA bill the extra-lead and extra-lift items appear as ordinary schedule items with their own quantities, so a deviation on the parent excavation item usually drags a proportionate deviation in the extras with it — worth remembering when you prepare the deviation statement.

Practical checks before you bill it

  • Quote the schedule's own slab convention — departments differ on slab lengths and on whether "part thereof" counts as a full slab.
  • Do not pay manual lead extras and mechanical carriage on the same quantity over the same distance — one replaces the other beyond the changeover point.
  • Lift is not payable merely because a trench is deep; the basic item for a stated depth range already covers working at that depth. Extra lift applies to raising the spoil beyond the initial lift, as defined in your schedule.
  • Where earth is first stacked and later re-carried, the second movement is a fresh lead from the stack — but only if the re-handling was ordered or is provided for in the contract.
These figures are an educational aid for quick checks. Always verify against your organisation's schedule of rates, the governing IS codes and the contract before use.

Related tools & reading