Works estimation · Tendering · Agreements · Billing — one platform contact@estimotor.online
Home › Resources › RA-Bill Checklist

RA-Bill Scrutiny Checklist — Printable Proforma

A 24-point pass-through for checking a running-account bill before it is put up for payment. Print one copy per bill with the button below or Ctrl + P — the site header and buttons drop out of the printout automatically.

Measurement-sheet proforma ← Back to Resources

RUNNING-ACCOUNT BILL — SCRUTINY CHECKLIST

(to accompany the bill file; tick each point or record why it does not apply)
Name of work:
Agreement No.:
Bill No.:
Contractor / Agency:
Date:
No.Point of check✔Remarks
A — Measurements & Measurement Book
1Measurements recorded in the MB, dated and signed by the recording JE, and test-checked by the AE to the prescribed percentage.
2Contractor's signature obtained in the MB accepting the measurements.
3Up-to-date quantities in the bill agree with the MB; quantity since the previous bill correctly derived (this bill minus previous bill).
4Deductions (openings, voids, deduct items) accounted for; no measurement entered twice across bills.
5Hidden work (foundations, reinforcement, work since covered) supported by measurements taken before covering.
B — Agreement & rates
6Item descriptions, units and rates in the bill tally with the agreement schedule; premium/rebate (percentage above/below) applied exactly as tendered and not applied twice.
7Quantities beyond deviation limits paid at the sanctioned deviated rates, not silently at agreement rates.
8Extra and substituted items supported by sanctioned analysis of rates within the accepting authority's financial powers.
9Part-rate payments (incomplete items) clearly marked, with the withheld portion identified for release in a later bill.
10Time extension position verified; compensation for delay, if leviable, considered before payment.
C — Recoveries & advances
11Security deposit deducted at the prescribed rate on the gross work done since the previous bill.
12Cost of departmental materials issued to the contractor recovered at the issue rates in the agreement.
13Secured advance on materials at site within the permissible percentage, supported by an indenture, and earlier secured advance recovered as the material is consumed.
14Mobilisation/machinery advance instalments and interest, where applicable, recovered on schedule.
15Statutory deductions (income tax, GST as applicable, labour cess) worked out on the correct base and shown in the memorandum of payment.
16Other recoveries — hire charges of departmental machinery, water/electricity, penalties — brought forward and deducted.
D — Statements & annexures
17Deviation statement enclosed where quantities deviate, with reasons recorded and sanction obtained where limits are crossed.
18Material consumption statement compares theoretical consumption with issues; excess/short consumption explained and recovery made where due.
19Escalation claim, if admissible under the contract, computed for the correct period with the notified indices and supported by its worksheet.
20Memorandum of payment arithmetic checked: gross value, recoveries, net payable and figure in words all agree.
E — Final bill only
21Work physically complete; completion certificate recorded and defect rectifications, if any, carried out.
22All outstanding advances (secured, mobilisation) fully recovered; balance departmental materials returned or their cost recovered.
23Final quantities reconciled with the MB for the whole work; "no further claim" acceptance obtained from the contractor.
24Release of security deposit / performance guarantee noted for action only after the defects-liability period as per the agreement.
Prepared byJunior Engineer
Checked byAssistant Engineer
Signature of Contractor(where acceptance is required)
Note: the points above reflect common works-manual practice; add or strike points to suit your organisation's codes and the conditions of the particular agreement. Inside eTAB Works-Estimator™ most of these checks are enforced automatically — carried-forward quantities, part rates, secured-advance recovery, deviation and consumption statements are generated from the same data as the bill itself.